Someone is over capacity on a day when the hours booked for them that day add up to more than their capacity. Pondria checks this per person and per day, after holidays and approved time off are taken out. It warns you and never blocks the booking, so you decide whether to rebalance the plan or agree to the extra load.
How Pondria works out capacity
Each person's capacity is calculated one day at a time:
- Start from the hours their Working schedule gives that weekday.
- Apply the days of every calendar they are subscribed to. A public holiday is usually a full day off, which removes 8 hours.
- Subtract approved time off. Time off that is still Pending does not count yet.
A day with no capacity left, such as a weekend, a full holiday or a full day of approved leave, is non-working time. Bookings put no hours on such a day and do not move them elsewhere, so a non-working day never shows as over capacity.
What puts a day over capacity
A day is over capacity when the hours booked across all projects are higher than that day's capacity. There is no tolerance, so even a fraction of an hour over counts. Bookings on Prospective projects count at their full hours, so the Capacity page shows the load your team would carry if every prospect lands. The page on how win probability works explains where weighting does apply.
The usual causes are:
- Two or more bookings on the same day that together exceed the person's hours.
- A booking with the same Hours per day across a shorter weekday, for example 8 hours a day on a 4-hour Friday. A booking entered as a Share of capacity also becomes one fixed number of hours per day.
- Partial leave or a partial holiday that shortens a working day while the bookings stay the same.
Where it shows up
- While you book, the allocation form says on how many days the person would be over capacity, how high the load goes and on which dates, and still lets you save.
- On the Capacity page, days over capacity show in orange with a warning sign. Above the chart, a callout says how many people are over capacity in the chosen dates and how many days still need a decision, and Review and resolve opens the overview. For a view of more than 100 people, the callout checks everyone only when you choose Check everyone.
- On the Overview, the Act now section lists people who are over capacity in the next 12 weeks, with the number of those days in the next four weeks and a Rebalance link to their plan.
- A team's Planning tab marks people as Over capacity, and both Team utilization and a person's Utilization tab count their Days over capacity.
Pondria sends no notifications or emails about days over capacity.
What you can do about it
The overview puts everyone who is over capacity on one timeline across the Capacity page's dates, which the date button in the overview changes too. Each person's line marks their days over capacity, coloured by how far over each day goes, with today marked. Next to it are the days still to decide, the peak load and its day, and the hours too many. Days in a row form one stretch, and a weekend or other day off in between does not break it.
Two options change what the timeline includes. Show agreed days adds the stretches already agreed, in a pale tone. Include days before today, on by default, adds the days that have passed, in grey. Anyone who can open the overview, Members included, can use Find in grid to jump to the next day still to decide on the chart.
Click a stretch to open it under the person, or click a person's name or figures to open their first stretch still to decide; the arrows beside the chart step to their previous and next stretch. It shows a bar per day, with each project's hours stacked on top of any time off, against a dashed line at the person's usual day, and a row per project with its hours on each day. From there an Owner or Manager can:
- Use the recommended fix, the smallest change one project can make on its own to bring every day within capacity, such as capping that project at a number of hours per day on the days over capacity.
- Change a project's hours on any day of the stretch. Each project's row keeps a running total of the change, and the bars update as you type. Save keeps the changes, and Save and mark the rest as agreed also agrees whatever is still over capacity.
- Mark the whole stretch as agreed in one step.
- Open the person's plan at those dates, to move a booking or hand the work to someone else.
Days in the past are read-only.
Agreeing to an overload
Sometimes a crunch week is a deliberate choice. Marking it as agreed records that decision with an optional reason:
- The day stays on the chart as Agreed, in a pale tone, and stops counting in the callout, on the Overview and in the utilization counts.
- It opens again by itself if that day goes further over capacity than the worst day in the agreed stretch was at the time.
- In the overview, Mark as agreed covers every day of the stretch. From a day in a person's plan, Mark as agreed covers that one day.
- Only a day that is already over capacity can be agreed, so future warnings cannot be silenced in advance.
To undo one, tick Show agreed days in the overview, open the agreed stretch and choose Remove agreement.
Who can see and do what
| Role | Sees on the Capacity page | Can change |
|---|---|---|
| Owner | Everyone in the organization | Every booking, and agreements |
| Manager | People in the teams they manage, plus themselves and their own teammates | Bookings on projects of the teams they manage, and agreements |
| Member | Themselves and the people in their own teams | Nothing, as the plan is read-only |
| Viewer | Nothing, since the Capacity page is not part of their view | Nothing |
In the Overview's Act now section, a Member sees only their own entry, "You're over capacity". A Viewer sees only the Overview and the projects shared with them, without capacity figures. The page on which projects a Viewer can see explains that access.